Newsroom

Print

Roadway construction at Meadowbrook redevelopment

Post Date:03/06/2017 5:05 PM

 UPDATE 3/22/17

As part of the Meadowbrook redevelopment,  the roadway construction includes improvements to two intersections: 1) Roe Avenue at 91st Street and 2) Nall Avenue and Meadowbrook Parkway.

Both improvements consist of widening the roadway to incorporate pedestrian crosswalks with an island and left turn lanes at the intersections.

The Roe Avenue pedestrian island construction will require the contractor to close the roadway during working hours starting tomorrow, Thursday, March 23rd and continue into next week. Final paving on Roe Avenue is anticipated mid-week.

The Nall Avenue pedestrian island construction will begin next week and traffic will be reduced to one lane in each direction. Final paving on Nall Avenue is anticipated mid-week also.

Please be alert when driving through these areas, as the contractor will be changing traffic control based on their activities. 

****************************************************************

As part of the Meadowbrook redevelopment, the roadway construction includes improvements to two intersections: 1) Roe Avenue at 91st Street and 2) Nall Avenue and Meadowbrook Parkway. Both improvements consist of widening the roadway to incorporate pedestrian crosswalks and left turn lanes at the intersections.

The contractor started work on the Roe Avenue improvements Monday by milling the surface of the existing roadway. Crews anticipate started on the Nall Avenue improvements on Wednesday. The contractor is scheduled to be completed with this intersection work in three weeks, weather permitting.
It is anticipated that the contractor will be working daily from 8:30 a.m. to 4:30 p.m.

Please be alert when driving through these areas, as the contractor will be changing traffic control based on their activities.  